The Chicago Fire says McDonald's Park will open in 2028. The city's own schedule for the roads, parking garage, plaza and river wall around the stadium has a later date. Those are set to begin in the fourth quarter of 2026 and finish in the second quarter of 2031.
Those two dates are about three years apart, and a South Loop purchase near Roosevelt Road, Wells Street or Clark Street falls between them. The stadium has the shortest timeline at The 78. If you are weighing a home within walking distance of the site, the 2031 date and the new apartments going up next door will shape your first several years of ownership more than the opening match will.
Three Timelines on One 62-Acre Site
The 78 is Related Midwest's 62-acre former railyard along the Chicago River, just south of Roosevelt Road. The development team says it plans to invest $8 billion in the full buildout. Three separate projects share that ground, and each runs on its own schedule.
| What is being built | Who pays | Where it stands | Scheduled finish |
|---|---|---|---|
| McDonald's Park, 22,000 seats | Chicago Fire FC, privately financed | Broke ground March 3, 2026; concrete going in at the seating bowl this fall | 2028, per the club |
| Roads, city garage, plaza, river wall, Metra work | $424.9 million in TIF, approved July 15, 2026 | Construction scheduled to start Q4 2026 | Q2 2031 |
| Up to 10,000 homes, 20% affordable | Private development | Allowed under the site plan | No date set |
The stadium is moving fast. In its October 9 site update, Chicago YIMBY reported that the west tower crane had already been removed and concrete was still being poured. Its August update described the seating bowl taking shape around the southwest corner and south end. Before the infrastructure work is even scheduled to start, the stadium already has a visible bowl.
Why the Roads Take Longer Than the Stadium
The 78 sits about 40 feet below Roosevelt Road. According to WTTW's coverage of the city's presentation, the planned plaza and garage are what close the gap between Roosevelt and the Wentworth-to-Wells connection. Before new streets can reach Roosevelt, the garage and the plaza above it have to be built to bridge that grade.
The Department of Planning and Development's July 13 finance committee packet breaks down the $424.9 million:
- Public access structure and plaza over a 1,200-space city-owned garage: $216.4 million, about 51% of the total
- New roadways on 13th, 14th and 15th streets, two phases of LaSalle Street, and Wells Street modifications: $105.7 million
- Metra improvements: $36.1 million
- River wall: $33.7 million
- Clark Street pedestrian connector: $12.4 million
- Clark Street improvements: $12.2 million
- Roosevelt Road improvements: $8.4 million
More than half the budget goes to one structure, the garage and the plaza on top of it, and that structure is what ties the site to the street grid. The city's packet calls the infrastructure "critical" for connecting the site to the surrounding neighborhoods and allowing future development across all 62 acres. Once finished, the roads and garage go to the city. The river wall and plaza will be privately operated and maintained.
At full buildout, the city describes 6 acres of public open space, including a half mile of improved riverfront with new bike, pedestrian and water connections. The current phase commits to about 2.75 acres of new green space. Read side by side, the two calendars suggest the stadium's first seasons will overlap with active road, garage and river wall construction. The riverfront park in the renderings belongs to the later timeline.
Game Days, as Currently Planned
How often the stadium is busy matters most to the blocks closest to it, and the latest public figures are still projections. In June 2025, Chicago YIMBY reported an estimate of about 17 Fire home matches and about 10 other large events a year, plus smaller private events. The same report listed the 1,300-space Roosevelt Collection garage as additional parking for stadium visitors. The club itself describes year-round concerts, international matches and community programming.
Transit is the piece buyers most often get wrong. A Red Line stop at 15th and Clark was proposed years ago, but Block Club Chicago reported in September 2025 that it is not in the current plans. The plans at that time called for a dedicated bus route, a water-taxi stop, and 2,800 to 3,000 game-day parking spaces across onsite and nearby facilities, with shuttles from lots farther away. The 2026 infrastructure package funds Metra track improvements, not a new station. On game days, the Fire will lease the 1,200-space city garage.
So a listing that advertises being "steps from a new train stop" is describing a plan that was dropped. A home close to the stadium will be close to game-day traffic heading for garages and shuttles.
The Housing That Arrives Before The 78's Housing
The 78 is permitted for up to 10,000 homes, but no start date has been set for the first residential tower. Rental supply right next to the site is arriving sooner.
- Riverline, 1010 S. Wells. 388 rental units. Chicago YIMBY reported it at the 20th floor of a revised 22-story design on September 25, and close to topping out on October 9.
- Riverline, 910 S. Wells. A planned 28-story, 350-unit tower whose pile permit was issued July 14, 2026.
- Southbridge 1C, 2305 S. State. 80 mixed-income apartments in a 12-story building, expected to be finished in June 2027.
The Railyards proposal across the river would place residential and commercial buildings around a possible White Sox ballpark. Urbanize Chicago describes it as an early feasibility-stage plan with no set timeline.
Developers are already treating the stadium as part of their pitch. In May, Crain's Chicago Business reported that Lendlease was marketing The Cooper at Southbank to investors partly on The 78's momentum and a supply-constrained downtown rental market. Across the wider Chicago market, MMG's Q3 2026 report found that apartment absorption over the trailing four quarters lagged new deliveries, while the citywide construction pipeline stood at 1.7% of inventory, compared with 2.7% nationally.
This matters for a South Loop condo owner. The amenities a buyer may be paying for, including the riverfront, the plaza and the finished street grid, run on the 2031 schedule. Competing new units within a few blocks are going up now. For the next few years, an owner who decides to sell or rent out a unit near Wells and Roosevelt will be doing it alongside brand-new rental towers.
Where the Ward and Neighbors Stand
Ald. Pat Dowell of the 3rd Ward, whose ward includes the site, supported the stadium after a series of community meetings and asked for more pedestrian access on the south side and traffic calming on Clark Street. At the July vote, City Bureau quoted her on why the infrastructure comes first:
"We need density in this city, and that density is made possible through privately financed vertical development. We cannot achieve this without the necessary physical infrastructure."
When the Fire broke ground in March, a coalition of neighborhood groups called for a community benefits agreement and more input from residents, Block Club Chicago reported. In an April story on the prospect of two stadiums in the South Loop, Block Club found neighbors divided. Some raised traffic, quality of life, affordability and small businesses. Others welcomed more activity and more transit options.
Pricing a Home Next to a Site Still Under Construction
Any effect the stadium has on nearby condo values is still a forecast. There is no recorded sales history next to a finished McDonald's Park to compare against, so any "stadium premium" in an asking price is a seller's estimate of the future.
That future comes in stages. The opening match is expected in 2028. The garage, plaza, new streets and river wall are scheduled to be finished by mid-2031. The first homes at The 78 do not yet have a start date. A buyer planning to own for seven or more years would see all three stages. A buyer who may sell within three years would likely be listing while the roads are still under construction and while Riverline's 388 and 350 units are competing for the same downtown renters and buyers.
Building location adds another layer. The homes facing the future riverfront and plaza are the same homes facing the garage entrances and new streets, and those streets are scheduled for construction from late 2026 through 2031. How much each of those matters depends on the specific building, its floor and its exposure. That is something to assess unit by unit before deciding on a price.
Quick Answers
Is a Red Line station coming to The 78? Not under current plans. The 15th and Clark stop is not included. The funded work covers Metra track improvements, and the plans also call for a bus route and a water-taxi stop.
Who owns the new garage? The city. The 1,200-space garage will be publicly accessible, and the Fire will lease it on game days.
When is the riverfront open space scheduled to be finished? It is part of the infrastructure package, which is scheduled to run from Q4 2026 to Q2 2031. The city has not set a separate date for the riverwalk.
If you are looking at a home near Roosevelt and Wells, it helps to have someone match that building's exposure to the actual construction timeline before you settle on a number. Cara L Buffa has represented downtown buyers and sellers for more than 30 years, and she will go through The 78's timeline with you for the specific building you are considering. Work directly with Cara and request a personal consultation.